In terms of acquisition planning, what factor does 'when' refer to?

Enhance your CCCM certification with our engaging quiz! Tackle multiple choice questions, flashcards, and detailed explanations to solidify your contracts management skills and ace your exam.

The factor 'when' in the context of acquisition planning is centered around the delivery schedule of goods and services. This aspect is crucial because understanding the timing of when goods or services need to be delivered directly impacts the overall project timeline and resource allocation. It ensures that all components are available when needed, aligning with the project's objectives and deadlines.

In acquisition planning, having a clear delivery schedule helps to synchronize various activities, reduce delays, and effectively manage procurement resources. This focus on 'when' also allows teams to address any potential scheduling conflicts early in the process, ensuring a smooth transition from procurement to project execution.

Other options, while relevant to acquisition planning, do not encapsulate the 'when' factor as directly as the delivery schedule does. For instance, the selection of the procurement team influences how effectively the acquisition process runs but does not pertain to timing. Similarly, the timeline for project completion and the review period for bids are critical elements, but they focus more on broader scheduling and procedural steps rather than the specific timing of delivery.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy